Documents
Works plan
Coming soonWhat is planned for the building, what it costs and what is in the repair fund.
Repair fund
€18,640.52
As of 31/10/2026
€295.38 comes in each month (€0.45/m²)
Planned in total €72,730.00
2030
Estimated cost- Küttesüsteemi tasakaalustaminePlanned€6,500
2029
- Keldri niiskustõke ja drenaažPlanned€14,000
2028
- Trepikodade värviminePlanned€9,600
2027
- Katuse remontOtsus üldkoosolekul 11.12.2026; remondifond ja laenGetting quotes€38,400
- Trepikoja 2 välisuksHääletus kuni 4.12.2026Planned€2,380
2026
- Trepikoja 1 LED-valgustusDone€1,720
- Katuse ülevaatusAkt 14.10.2026Done€450
- Trepikoja 2 LED-valgustusDetsembrisIn progress€1,850